Orange Coil

Tempest

TransAlta Corporation (TransAlta) through its wholly owned subsidiary TransAlta Coaldale Wind L.P. by its General Partner TransAlta Coaldale Wind Inc. plans to build, own and operate the Tempest Wind Power Project (the Project or Tempest). A transmission line to connect the Project to the grid will be applied for under a separate application. This webpage will be updated with new information as it becomes available.

Tempest Wind Power Project

TransAlta started developing Tempest in 2006. This included collecting wind data, talking with landowners, collecting environmental data, and conducting required analysis per Alberta Utilities Commission (AUC) Rule 007. The Project was submitted to the AUC on December 20, 2022 (Proceeding 27726) and received the Approval (27767-D02-2023) and Permit and Licence (27767-D03-2023) on April 28, 2023.  

The Project, as applied, is a 99-megawatt (MW) wind project located approximately 15 km east of Stirling, Alberta, in Warner County. The Project will consist of 22 Vestas, V150 4.5 MW wind turbines. The current target commercial operation date for the Project is Q4 2026.

TransAlta applied for a Development Permit (Development Permit No. 23-29) from the County of Warner No. 5 on June 6, 2023, and received approval on July 19, 2023, with the permit becoming effective on August 9, 2023. 

If you have any questions regarding the wind power project, please contact us using the information below. 

Phone: (877) 547-3365 Extension 1
Email: projects@transalta.com

Reference Documents

Mailout to stakeholders – November 2022
AUC Filing – Proceeding Number 27767
Mailout to stakeholders – September 2022
Community Engagement session print out – September 2022
Mailout to stakeholders – July 2022

Tempest Wind Power Connection Project 

As part of our ongoing development efforts, the construction of a transmission line to connect the Project to the electrical grid will also be required.  

The Tempest Wind Power Connection Project will consist of approximately 20 km of new 138-kilovolt (kV) transmission connecting the approved Tempest wind farm substation in SE 19-7-17 W4M and connected to an existing 138 kV line approximately 1 km north of the Chin Reservoir.  

Preliminary route options have been developed to collect feedback from landowners within 800 m of the proposed routes. Additional consultation is ongoing, with a tentative date of June 2024 for applying to the AUC. AUC approval is anticipated to be received in Fall 2025.

If you have any questions regarding the connection project, please contact us using the information below. 

Toll free number: 1 888-474-1702 
Email: transaltatempest@maskwaenv.com

Reference Documents

Project Overview
Need Overview: Transmission Development Information for Stakeholders
Tempest Newsletter Map
Tempest Strip Maps

Related Facilities